PROCEDURE FOR INITIAL PRODUCTION PART (IPP)

PROCEDURE FOR INITIAL PRODUCTION PART(IPP)


Quantity considered for Initial Part /Pilot Lot for submitting to the customer is as required by Customer.




First Production Parts (Initial Part /Pilot Lot) are identified by special identification tag called Initial Part Tag to differentiate those from normal parts for in-house (Identified by Internal IPP Tag) and at Customer End (IPP Tag).


All Characteristics specified in drawing are checked for minimum 5 parts each lot & recorded in IPP Inspection Report & list of all Initial Parts are recorded in Initial Part Log Book.


Inspection Reports and other reports as per Customer Requirement for each initial part/lot if any is kept properly and submitted to Customer and approval is taken if required.


If Samples /IPP gets rejected by Customer, then the non-conformity procedure will be applicable and parts will be scrapped both at in-house and Customer end.



Machine used for production of Initial Parts to be identified with IPP Board.


Initial Parts to be kept away from production in lock and key condition in IPP area.